The A-1 Total Service Lining team has been busy at the Grizzly Creek Dam project in Northern CA. We finally cut out and removed the obstruction, which was 125ft up inside the pipe.
The team cut holes in the obstruction and ran heavy-duty chain through it. We pulled out several smaller pieces before pulling out the 12FT x 18” round ball of metal and mud from the discharge end of the pipe. This portion of the project took all week to accomplish. Winches, snatch blocks, robotics and a great team all had a hand in this success.